API Tech Transfer Checklist: 28 Checks Before Scale-Up at a CDMO

API technology transfer to a CDMO involves dozens of handoffs between R&D, the receiving site, Quality and Regulatory Affairs. This checklist lists what needs to be in place before scale-up batches, with a suggested owner and the evidence that shows each item is actually done.

API tech transfer checklist: 8 phases, 28 checks, free Excel template

Download the free Excel version with status tracking, due dates and a progress count. No sign-up needed.

This is a project-coordination aid. It does not replace your quality system, SOPs, quality agreement or regulatory advice.

How to use this checklist

  • Agree it at kickoff: review the list with the CDMO and remove items that do not apply.
  • One owner per item: name a single accountable person, not a team.
  • Close on evidence: an item is done when the receiving side accepts the evidence, not when the sender says it is finished.
  • Review weekly: check open items against the launch or filing date.

1. Governance and scope

Set up who decides, who coordinates and what “transferred” means before technical work starts.

Checklist itemOwnerEvidence of completion
Named transfer coordinator on both sponsor and CDMO sideSponsor PM / CDMO PMProject charter or RACI naming both coordinators
Transfer scope and success criteria agreedSponsor PM, QAApproved transfer plan or protocol
Integrated plan linked to the launch or filing dateSponsor PMBaselined schedule with critical path
Decision and escalation route agreedSponsor PM / CDMO PMGovernance calendar and escalation matrix
Quality agreement in placeQA (both sides)Signed quality agreement

2. Process knowledge

Transfer the reasoning, not just the documents.

Checklist itemOwnerEvidence of completion
Process description includes the rationale for operating rangesR&DProcess package / development report
Difficult steps, observed failure modes and troubleshooting history documentedR&DProcess risk assessment and lessons log
Knowledge does not depend on one person; structured walk-throughs held and recordedR&D / CDMO technicalSession records and Q&A log
Every open technical question has an owner and a due dateSponsor PMQ&A log with verified closure

3. Analytical readiness

The receiving lab must be able to test the product before batches depend on it.

Checklist itemOwnerEvidence of completion
Method list and transfer approach agreed for each methodAnalytical (both sides)Analytical method transfer protocol
Reference standards and impurity markers available at the receiving siteAnalyticalInventory list with CoAs
Method transfer completed against agreed acceptance criteriaAnalytical / QAApproved method transfer report

4. Equipment and scale

Plant equipment behaves differently from the lab. Assess the differences before declaring readiness.

Checklist itemOwnerEvidence of completion
Equipment comparison covers mixing, heat removal, charging, filtration and dryingCDMO technicalEquipment gap assessment
Scale-up risks assessed and supporting studies plannedR&D / CDMO technicalScale-up risk assessment and study plan
Need for engineering or demonstration batch decidedTechnical leads / QARecorded decision with rationale
Cleaning and cross-contamination assessed for shared equipmentCDMO QACleaning assessment

5. Materials and supply

Late materials are one of the most common reasons transfer batches slip.

Checklist itemOwnerEvidence of completion
Raw material specifications and approved suppliers alignedSupply chain / QASpecifications and supplier approvals
Long-lead materials ordered against required-by datesSupply chainPurchase orders tracked against the plan
Quantities of starting materials and intermediates confirmed for all planned batchesSponsor PM / Supply chainMaterial requirements plan

6. Documentation and training

Agree what “complete” means for every deliverable so handoffs do not bounce back.

Checklist itemOwnerEvidence of completion
Documentation package list agreed, with acceptance criteria for each itemSponsor PM / QADeliverables register
Master batch records drafted and reviewedCDMO / QAApproved master batch record
Operators and analysts trained on the transferred processCDMOTraining records

7. Validation and regulatory

Quality and regulatory decisions stay with the designated specialists. The plan makes sure they happen on time.

Checklist itemOwnerEvidence of completion
Validation strategy agreed (approach and number of batches)QA / Technical leadsValidation plan or protocol
Regulatory impact assessed (site change, variation or supplement needs)Regulatory AffairsRegulatory impact assessment
Change control raised and tracked to closureQAChange control record

8. Readiness review

A green schedule is not readiness. Review the evidence.

Checklist itemOwnerEvidence of completion
Evidence reviewed: completed items, open technical work and unresolved deviations kept separateSponsor PM / QAReadiness review minutes
Every open item has an owner and a decision dateSponsor PMAction log
Go / no-go decision made by the designated approversQA / Technical leadsSigned readiness decision

Four key risks in API tech transfer, and how to avoid them

Most transfer delays stem from coordination, not chemistry. They usually start as blind spots: issues that are rarely owned until they surface at scale-up. The checklist helps bring these into focus early:

  • Documents that lack the reasoning behind them
  • Knowledge held by a single person
  • Equipment mismatches that were never assessed
  • Handoffs without agreed acceptance criteria

We explain each in API Technology Transfer to a CDMO: 4 Risks & How to Fix Them.

Frequently asked questions

What should an API tech transfer checklist include?

It should cover governance and scope, process knowledge, analytical method transfer, equipment and scale assessment, materials, documentation and training, validation and regulatory impact, and a final readiness review. For each item, record an owner and the evidence that shows it is complete.

Who owns the tech transfer checklist: the sponsor or the CDMO?

Both sides contribute, but one named coordinator should own the integrated checklist and plan. Individual items are owned by the relevant function on either side, and quality and regulatory approvals remain with the designated specialists.

Is this checklist enough for GMP compliance?

No. It is a project-coordination aid. It helps teams see gaps early, but it does not replace your quality system, SOPs, quality agreement or regulatory advice.

Track it live instead of in a spreadsheet

A spreadsheet works for one transfer. When you run several with different CDMOs, PMSoft Pharma keeps owners, due dates and evidence in one live view. Request a demo.